Docs / Engineering Consultancy / How do I manage drawings, their revisions and their approval?

How do I manage drawings, their revisions and their approval?

The worst thing that happens on site is a worker building from an old revision. The cure is one known approved revision per drawing.

Adding a drawing

  1. From the project page open DrawingsFigure 1.
  2. Add a drawing with its number, title and discipline: architectural, structural, MEP, civil, other.
  3. Upload the first revision file (A) with a change description.

Revisions and approval

  1. With every amendment upload a new revision (B, then C…); the previous one becomes superseded automatically.
  2. Move the status: draftinternal reviewclient reviewapproved.
  3. On approval the system records who approved it and when.
  4. From Engineering → DrawingsFigure 2 — you see every project’s drawings and can filter by discipline and status.

Notes

  • Never send a drawing to site unless its status is approved; a draft in a contractor’s hands is a cost you will pay.
  • Write the change description on every revision; six months later you will not remember why the drawing changed.
  • A superseded revision is kept, never deleted; it is your evidence in any dispute.

Screenshots

How do I manage drawings, their revisions and their approval?
Figure 1
How do I manage drawings, their revisions and their approval?
Figure 2

Try what you just read on your own data

Open a free 7-day trial — no credit card, with your own company link in minutes.